Project Name: Central Berkeley WWTP Flow Diversion West Phase 2
Projected Start Date: Spring of 2019
Project Contacts: Clarence Kornegay and Mark Waters
Project Description: The proposed modifications will divert a portion of the existing flow from Lower Berkeley Wastewater Treatment Plant (NPDES NO. SC0046060) to Central Berkeley Wastewater Treatment Plant (NPDES NO. SC0039764).

Division I includes the installation of approximately 10,175 LF of dual 18" FM (20,350 LF total), 475 LF of 36" gravity sewer main, and all associated appurtenances.

Division II includes the installation of approximately 14,580 LF of 24" FM and all associated appurtenances.

Division III includes one triplex submersible pump station, approximately 45 LF of 36" gravity sewer main, 108 LF of 24" force main, and all associated appurtenances.
Project Map: Central Berkeley WWTP Flow Diversion West Phase 2 – Divisions I, II, & III
   
Project Name: FY17 Pump Station R&R
Projected Start Date: In Construction
Project Contacts: Clarence Kornegay and Mark Waters
Project Description: Rehabilitation of pump station including new pumps, top slab, and header. PS053 and 202 wetwell will remain, but interior will be renovated. PS111 will receive a new wetwell. New grading, pavement, and force main piping. By-pass pumping will be installed for use during construction on PS053 and 202.
Project Map: FY17 Pump Station R&R
   
Project Name: Nexton Water Main Extension
Projected Start Date: Spring of 2019
Project Contacts: Clarence Kornegay and Mark Waters
Project Description: Install approximately 2,260 LF of 12" water main along Nexton Parkway to tie in with existing main along US 176.
Project Map: Nexton Water Main Extension
   
Project Name: I-26/Jedburg Road Interchange Relocation
Projected Start Date: Spring of 2019
Project Contacts: Ellen Hill and Mark Waters
Project Description: This project consists of the relocation of existing water and sewer lines due to SCDOT I-26/Jedburg Rd widening project. Water lines to be relocated consists of: 1,850 LF of 16" water main, 2,675 LF of 14" water main, and 50 LF of 6" water. In addition, sewer lines to be relocated consists of: 1,185 LF of 16" gravity sewer, 3,025 LF of 14" force main, and 2,020 LF of 8" force main.
Project Map: I-26/Jedburg Road Interchange Relocation
   
Project Name: Nucor Water Tower Painting
Projected Start Date: Spring of 2019
Project Contacts: Ellen Hill and Mark Waters
Project Description: This project involves surface preparation, cleaning and recoating of the exterior of an existing 500,000 gallon elevated storage tank.
Project Map: Nucor Water Tower Painting